1812 Eglinton Ave W is a development site in Briar Hill-Belgravia, Toronto, with two development applications on the City's file. The largest is an Official Plan and/or Zoning By-law Amendment for 50 storeys and 43,151 m² of gross floor area. Two files are under review or before the Ontario Land Tribunal, the most recent submitted on 8 May 2023. It sits in Ward 8, Eglinton-Lawrence.
Site Plan Approval
Under reviewA site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.
35 storeys, 31,488 m² GFA
- Application
- Site Plan Approval
- City file number
- 23 142988 NNY 08 SA
- Status, the City’s wording
- Under Review
- Submitted
- 8 May 2023
- Storeys
- 35
- Gross floor area
- 31,488 m²
- Applicant of record
- Not named in the City’s record
Also filed under 1818 Eglinton Ave W.
Official Plan and/or Zoning By-law Amendment
Under reviewAn amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.
50 storeys, 43,151 m² GFA
- Application
- Official Plan and/or Zoning By-law Amendment
- City file number
- 21 127937 NNY 08 OZ
- Status, the City’s wording
- Under Review
- Submitted
- 16 March 2021
- Storeys
- 50
- Gross floor area
- 43,151 m²
- Applicant of record
- Not named in the City’s record
Also filed under 1818 Eglinton Ave W.
Questions about 1812 Eglinton Ave W
Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.
What is being built at 1812 Eglinton Ave W?
The largest application on file proposes 50 storeys and 43,151 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.
Has the application at 1812 Eglinton Ave W been approved?
Not yet. The file is recorded by the City as “Under Review”. Under review by City Planning. The application has been circulated to divisions and commenting agencies, and the statutory decision timeline under the Planning Act runs from the date it was deemed complete. Written submissions carry the most weight at this stage, before a staff recommendation report is finalised.
How do I comment on a development application in Toronto?
Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.
What else is being built near 1812 Eglinton Ave W?
Other applications within 500 m are listed on this page, and every application in Briar Hill-Belgravia can be browsed by ward and by stage in the planning section.
What this page does not carry
Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.