torontopolis.ca Planning
My List
Ward 8 · Eglinton-Lawrence · Yorkdale-Glen Park

3019 Dufferin St

Toronto, Ontario
At the Tribunal 2 applications on file

About this site

3019 Dufferin St is a development site in Yorkdale-Glen Park, Toronto, with two development applications on the City's file. The largest is a Site Plan Approval for 33 storeys. One file is under review or before the Ontario Land Tribunal, the most recent submitted on 16 December 2016. It sits in Ward 8, Eglinton-Lawrence.

Site Plan Approval

Closed or refused

A site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.

33 storeys

Application
Site Plan Approval
City file number
18 124116 NNY 15 SA
Status, the City’s wording
Closed
Submitted
2 March 2018
Storeys
33
Gross floor area
Not in the City’s record
Applicant of record
Not named in the City’s record

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

33 storeys

Application
Official Plan and/or Zoning By-law Amendment
City file number
16 268010 NNY 15 OZ
Status, the City’s wording
OMB Approved
Submitted
16 December 2016
Storeys
33
Gross floor area
Not in the City’s record
Applicant of record
Not named in the City’s record

Questions about 3019 Dufferin St

Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.

What is being built at 3019 Dufferin St?

The largest application on file proposes 33 storeys. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.

Has the application at 3019 Dufferin St been approved?

Not yet. The file is recorded by the City as “OMB Approved”. Before the Ontario Land Tribunal. Jurisdiction has moved from the City to the Tribunal. The Tribunal may substitute its own decision, and the file commonly settles with revised plans rather than proceeding to a full hearing.

How do I comment on a development application in Toronto?

Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.

What else is being built near 3019 Dufferin St?

Other applications within 500 m are listed on this page, and every application in Yorkdale-Glen Park can be browsed by ward and by stage in the planning section.

What this page does not carry

Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.