Closed or refused 3 applications on file

About this site

31 Finch Ave E is a development site in Yonge-Doris, Toronto, with three development applications on the City's file. The largest is a Site Plan Approval for 31 storeys and 28,354 m² of gross floor area. Nothing on this site is currently before the City. It sits in Ward 18, Willowdale.

Site Plan Approval

Closed or refused

A site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.

31 storeys, 28,354 m² GFA

Application
Site Plan Approval
City file number
24 218689 NNY 18 SA
Status, the City’s wording
Closed
Submitted
26 September 2024
Storeys
31
Gross floor area
28,354 m²
Applicant of record
Not named in the City’s record

Also filed under 32 Olive Ave, 36 Olive Ave, 38 Olive Ave.

Site Plan Approval

Approved

A site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.

29 storeys, 26,745 m² GFA

Application
Site Plan Approval
City file number
21 227685 NNY 18 SA
Status, the City’s wording
Final Approval Completed
Submitted
19 October 2021
Storeys
29
Gross floor area
26,745 m²
Applicant of record
Not named in the City’s record

Also filed under 38 Olive Ave, 36 Olive Ave, 32 Olive Ave.

Official Plan and/or Zoning By-law Amendment

Closed or refused

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

29 storeys, 26,745 m² GFA

Application
Official Plan and/or Zoning By-law Amendment
City file number
21 227683 NNY 18 OZ
Status, the City’s wording
Closed
Submitted
19 October 2021
Storeys
29
Gross floor area
26,745 m²
Applicant of record
Not named in the City’s record

Also filed under 32 Olive Ave, 36 Olive Ave, 38 Olive Ave.

Questions about 31 Finch Ave E

Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.

What is being built at 31 Finch Ave E?

The largest application on file proposes 31 storeys and 28,354 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.

Has the application at 31 Finch Ave E been approved?

Nothing at this address is currently before the City. The most recent file is recorded as “Closed”. A re-submission on the same site under a new file number is common, so a closed application does not mean the site is finished.

How do I comment on a development application in Toronto?

Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.

What else is being built near 31 Finch Ave E?

Other applications within 500 m are listed on this page, and every application in Yonge-Doris can be browsed by ward and by stage in the planning section.

What this page does not carry

Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.