At the Tribunal 2 applications on file

About this site

4665 Steeles Ave E is a development site in Milliken, Toronto, with two development applications on the City's file. The largest is an Official Plan and/or Zoning By-law Amendment for 28 storeys and 16,065 m² of gross floor area. Two files are under review or before the Ontario Land Tribunal, the most recent submitted on 5 January 2016. It sits in Ward 22, Scarborough-Agincourt.

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

Application
Official Plan and/or Zoning By-law Amendment
City file number
16 100895 ESC 39 OZ
Status, the City’s wording
OMB Approved
Submitted
5 January 2016
Storeys
Not in the City’s record
Gross floor area
Not in the City’s record
Applicant of record
Not named in the City’s record

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

28 storeys, 16,065 m² GFA

Application
Official Plan and/or Zoning By-law Amendment
City file number
13 273308 ESC 39 OZ
Status, the City’s wording
Appeal Received
Submitted
3 December 2013
Storeys
28
Gross floor area
16,065 m²
Applicant of record
Not named in the City’s record

Questions about 4665 Steeles Ave E

Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.

What is being built at 4665 Steeles Ave E?

The largest application on file proposes 28 storeys and 16,065 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.

Has the application at 4665 Steeles Ave E been approved?

Not yet. The file is recorded by the City as “OMB Approved”. Before the Ontario Land Tribunal. Jurisdiction has moved from the City to the Tribunal. The Tribunal may substitute its own decision, and the file commonly settles with revised plans rather than proceeding to a full hearing.

How do I comment on a development application in Toronto?

Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.

What else is being built near 4665 Steeles Ave E?

Other applications within 500 m are listed on this page, and every application in Milliken can be browsed by ward and by stage in the planning section.

What this page does not carry

Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.