About this site

50-60 Eglinton Ave W is a development site in Yonge-Eglinton, Toronto, with four development applications on the City's file. The largest is an Official Plan and/or Zoning By-law Amendment for 58 storeys and 73,305 m² of gross floor area. Four files are under review or before the Ontario Land Tribunal, the most recent submitted on 12 April 2024. It sits in Ward 8, Eglinton-Lawrence.

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

58 storeys, 73,305 m² GFA

Application
Official Plan and/or Zoning By-law Amendment
City file number
24 135591 NNY 08 OZ
Status, the City’s wording
OMB Appeal
Submitted
12 April 2024
Storeys
58
Gross floor area
73,305 m²
Applicant of record
Not named in the City’s record

Also filed under 19 Henning Ave, 17 Henning Ave, 90 Eglinton Ave W.

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

39 storeys, 54,755 m² GFA

Application
Official Plan and/or Zoning By-law Amendment
City file number
20 229115 NNY 08 OZ
Status, the City’s wording
OMB Appeal
Submitted
14 December 2020
Storeys
39
Gross floor area
54,755 m²
Applicant of record
Not named in the City’s record

Also filed under 90 Eglinton Ave W, 17 Henning Ave, 19 Henning Ave.

Site Plan Approval

At the Tribunal

A site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.

39 storeys, 54,755 m² GFA

Application
Site Plan Approval
City file number
20 126681 NNY 08 SA
Status, the City’s wording
Appeal Received
Submitted
16 March 2020
Storeys
39
Gross floor area
54,755 m²
Applicant of record
Not named in the City’s record

Also filed under 17 Henning Ave, 19 Henning Ave, 90 Eglinton Ave W.

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

36 storeys, 27,354 m² GFA

Application
Official Plan and/or Zoning By-law Amendment
City file number
17 250825 NNY 16 OZ
Status, the City’s wording
OMB Appeal
Submitted
20 October 2017
Storeys
36
Gross floor area
27,354 m²
Applicant of record
Not named in the City’s record

Also filed under 60 Eglinton Ave W.

Questions about 50-60 Eglinton Ave W

Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.

What is being built at 50-60 Eglinton Ave W?

The largest application on file proposes 58 storeys and 73,305 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.

Has the application at 50-60 Eglinton Ave W been approved?

Not yet. The file is recorded by the City as “OMB Appeal”. Before the Ontario Land Tribunal. Jurisdiction has moved from the City to the Tribunal. The Tribunal may substitute its own decision, and the file commonly settles with revised plans rather than proceeding to a full hearing.

How do I comment on a development application in Toronto?

Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.

What else is being built near 50-60 Eglinton Ave W?

Other applications within 500 m are listed on this page, and every application in Yonge-Eglinton can be browsed by ward and by stage in the planning section.

What this page does not carry

Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.