6 Lloyd Ave is a development site in Junction Area, Toronto, with three development applications on the City's file. The largest is a Draft Plan of Condominium for 17 storeys and 43,736 m² of gross floor area. Three files are under review or before the Ontario Land Tribunal, the most recent submitted on 30 September 2021. It sits in Ward 5, York South-Weston.

Draft Plan of Condominium

Under review

A draft plan of condominium under s. 51 of the Planning Act, registering tenure so units can be conveyed separately. It does not change what may be built.

17 storeys, 43,736 m² GFA

Application
Draft Plan of Condominium
City file number
21 220130 WET 05 CD
Status, the City’s wording
Under Review
Submitted
30 September 2021
Storeys
17
Gross floor area
43,736 m²
Applicant of record
Not named in the City’s record

Site Plan Approval

Under review

A site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.

17 storeys, 53,072 m² GFA

Application
Site Plan Approval
City file number
21 176811 WET 05 SA
Status, the City’s wording
Under Review
Submitted
28 June 2021
Storeys
17
Gross floor area
53,072 m²
Applicant of record
Not named in the City’s record

Also filed under 161 Mulock Ave, 163 Mulock Ave, 167 Mulock Ave, 169 Mulock Ave, 171 Mulock Ave, 175 Mulock Ave.

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

Application
Official Plan and/or Zoning By-law Amendment
City file number
19 239452 WET 05 OZ
Status, the City’s wording
OMB Appeal
Submitted
22 October 2019
Storeys
Not in the City’s record
Gross floor area
Not in the City’s record
Applicant of record
Not named in the City’s record

Also filed under 161 Mulock Ave, 163 Mulock Ave, 165 Mulock Ave, 167 Mulock Ave, 169 Mulock Ave, 171 Mulock Ave.

Questions about 6 Lloyd Ave

Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.

What is being built at 6 Lloyd Ave?

The largest application on file proposes 17 storeys and 43,736 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.

Has the application at 6 Lloyd Ave been approved?

Not yet. The file is recorded by the City as “Under Review”. Under review by City Planning. The application has been circulated to divisions and commenting agencies, and the statutory decision timeline under the Planning Act runs from the date it was deemed complete. Written submissions carry the most weight at this stage, before a staff recommendation report is finalised.

How do I comment on a development application in Toronto?

Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.

What else is being built near 6 Lloyd Ave?

Other applications within 500 m are listed on this page, and every application in Junction Area can be browsed by ward and by stage in the planning section.

What this page does not carry

Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.