80 Union St is a development site in Weston-Pelham Park, Toronto, with two development applications on the City's file. The largest is an Official Plan and/or Zoning By-law Amendment for 49 storeys and 97,921 m² of gross floor area. Two files are under review or before the Ontario Land Tribunal, the most recent submitted on 9 November 2021. It sits in Ward 9, Davenport.

Draft Plan of Subdivision

Under review

A draft plan of subdivision under s. 51 of the Planning Act, creating new lots, blocks and in most cases new public streets.

Application
Draft Plan of Subdivision
City file number
21 235877 STE 09 SB
Status, the City’s wording
Under Review
Submitted
9 November 2021
Storeys
Not in the City’s record
Gross floor area
Not in the City’s record
Applicant of record
Not named in the City’s record

Also filed under 2 Union St.

Official Plan and/or Zoning By-law Amendment

At the Tribunal

An amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.

49 storeys, 97,921 m² GFA

Application
Official Plan and/or Zoning By-law Amendment
City file number
21 235872 STE 09 OZ
Status, the City’s wording
OMB Appeal
Submitted
9 November 2021
Storeys
49
Gross floor area
97,921 m²
Applicant of record
Not named in the City’s record

Also filed under 2 Union St.

Questions about 80 Union St

Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.

What is being built at 80 Union St?

The largest application on file proposes 49 storeys and 97,921 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.

Has the application at 80 Union St been approved?

Not yet. The file is recorded by the City as “Under Review”. Under review by City Planning. The application has been circulated to divisions and commenting agencies, and the statutory decision timeline under the Planning Act runs from the date it was deemed complete. Written submissions carry the most weight at this stage, before a staff recommendation report is finalised.

How do I comment on a development application in Toronto?

Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.

What else is being built near 80 Union St?

Other applications within 500 m are listed on this page, and every application in Weston-Pelham Park can be browsed by ward and by stage in the planning section.

What this page does not carry

Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.