90 Eastdale Ave
About this site
90 Eastdale Ave is a development site in Taylor-Massey, Toronto, with six development applications on the City's file. The largest is a Site Plan Approval for 41 storeys and 39,900 m² of gross floor area. One file is under review or before the Ontario Land Tribunal, the most recent submitted on 10 July 2024. It sits in Ward 19, Beaches-East York.
Site Plan Approval
Under reviewA site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.
41 storeys, 39,900 m² GFA
- Application
- Site Plan Approval
- City file number
- 24 178208 STE 19 SA
- Status, the City’s wording
- Under Review
- Submitted
- 10 July 2024
- Storeys
- 41
- Gross floor area
- 39,900 m²
- Applicant of record
- Not named in the City’s record
Part Lot Control Exemption
ApprovedAn exemption from part lot control under s. 50(7) of the Planning Act, lifting the restriction on conveying part of a registered lot or block.
- Application
- Part Lot Control Exemption
- City file number
- 20 219688 STE 19 PL
- Status, the City’s wording
- Approved
- Submitted
- 18 November 2020
- Storeys
- Not in the City’s record
- Gross floor area
- Not in the City’s record
- Applicant of record
- Not named in the City’s record
Site Plan Approval
Closed or refusedA site plan control application under s. 41 of the Planning Act. Use and density are already permitted; what is under review is siting, massing, the public realm interface, servicing, access, waste and landscaping.
37 storeys
- Application
- Site Plan Approval
- City file number
- 15 209998 STE 31 SA
- Status, the City’s wording
- Closed
- Submitted
- 20 August 2015
- Storeys
- 37
- Gross floor area
- Not in the City’s record
- Applicant of record
- Not named in the City’s record
Official Plan and/or Zoning By-law Amendment
Closed or refusedAn amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.
37 storeys
- Application
- Official Plan and/or Zoning By-law Amendment
- City file number
- 15 209995 STE 31 OZ
- Status, the City’s wording
- Closed
- Submitted
- 20 August 2015
- Storeys
- 37
- Gross floor area
- Not in the City’s record
- Applicant of record
- Not named in the City’s record
Official Plan and/or Zoning By-law Amendment
Closed or refusedAn amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.
24 storeys
- Application
- Official Plan and/or Zoning By-law Amendment
- City file number
- 10 119850 STE 31 OZ
- Status, the City’s wording
- Closed
- Submitted
- 18 February 2010
- Storeys
- 24
- Gross floor area
- Not in the City’s record
- Applicant of record
- Not named in the City’s record
Also filed under 2 Secord Ave.
Official Plan and/or Zoning By-law Amendment
Closed or refusedAn amendment application under ss. 17 and 34 of the Planning Act, to permit use, height or density the in-force Official Plan and Zoning By-law do not.
30 storeys
- Application
- Official Plan and/or Zoning By-law Amendment
- City file number
- 08 231740 STE 31 OZ
- Status, the City’s wording
- Closed
- Submitted
- 23 December 2008
- Storeys
- 30
- Gross floor area
- Not in the City’s record
- Applicant of record
- Not named in the City’s record
Also filed under 2 Secord Ave.
Questions about 90 Eastdale Ave
Answered from the City’s Development Applications dataset and the Planning Act. General information, not legal or planning advice.
What is being built at 90 Eastdale Ave?
The largest application on file proposes 41 storeys and 39,900 m² of gross floor area. Unit counts are not a field in the City's Development Applications dataset, so the number of homes is not stated here; where it exists it is in the planning rationale filed with the application.
Has the application at 90 Eastdale Ave been approved?
Not yet. The file is recorded by the City as “Under Review”. Under review by City Planning. The application has been circulated to divisions and commenting agencies, and the statutory decision timeline under the Planning Act runs from the date it was deemed complete. Written submissions carry the most weight at this stage, before a staff recommendation report is finalised.
How do I comment on a development application in Toronto?
Written submissions go to the assigned City planner and to your Ward Councillor, and they carry the most weight while a file is under review, before the staff recommendation report is finalised. The statutory notice, the community consultation meeting date and any submission deadline are not fields in the open dataset this page reads, so they have to come from the City's own record or the notice posted on the site.
What else is being built near 90 Eastdale Ave?
Other applications within 500 m are listed on this page, and every application in Taylor-Massey can be browsed by ward and by stage in the planning section.
What this page does not carry
Unit counts are not a field in the City’s Development Applications dataset; where the figure exists it is in the planning rationale filed with the application. Committee of Adjustment matters, which are minor variance (s. 45) and consent (s. 53), are a separate City stream and are not in this dataset at all. Statuses are read from a published extract rather than a live feed, so confirm the current position against the City’s own record before relying on it.